Construction Projects
Construction projects information and advisory
Temporary Domestic Water Shutdown at Buildings: 206 & 258 (691-21-120)
Area of Impact
As part of our continued effort to improve infrastructure across West Los Angeles Campus, construction crews will temporarily shut down domestic water service to multiple buildings on the WLA VA campus. The purpose of this shutdown is to transition the domestic water supply to a new source as part of the long-term water improvement project on the VA campus. Please see Exhibit A for map of shutdown locations.
Portable restrooms and bottled water will be provided, please see Exhibit A for restroom locations.
Please see the list of affected buildings and the water shutdown timeline below.
Dates & Times of Impact
Construction Start – 11/20/24
Construction Finish – 11/21/24
Contact(s)
If you have additional questions about this matter or require more information, please contact:
Khoa Do, Healthcare Engineer
Email: khoa.do1@va.gov
Phone:
UPDATED WLA Construction Advisory – Dewey Ave & Eisenhower Ave. Temporary Two-lane closure & closing of PL17 (691-23-120)
Area of Impact
As a part of our continued effort to improve infrastructure across VA West Los Angeles Campus, construction crews will be performing the following work for the installation of new water lines:
Construction crews will close off traffic lanes on sections of Dewey Ave, Eisenhower Ave & closing off PL17. For alternative parking, use PL16 & PL18. The affected areas will be inaccessible to vehicular traffic. Sidewalks will remain open for the duration of the work. Please see Exhibit A.
Dates & Times of Impact (weather permitting)
Dewey (a)
Construction Start: Ongoing
Construction Finish: 11/18/2024
Eisenhower (b)
Construction Start: Ongoing
Updated: Construction Finish: 11/28/2024
_________________________________________________________________________________________________
Construction crews will be working on the landscaping area, the area is closed to public. This work will not impact any road or sidewalk closure.
Bringham (c)
Construction Start: Ongoing
Updated: Construction Finish: 12/20/2024
_________________________________________________________________________________________________
Construction crews will close off a section of driveway in between B113 & B114. The affected areas will be inaccessible to vehicular & pedestrian traffic; however, sidewalks will remain open on the east side of Dewey Ave for the duration of the work.
Dewey Lateral (d)
Updated: Construction Start: Ongoing
Updated: Construction Finish: 12/09/2024
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Homa Shahpasandzadeh
Email: Homa.Shahpasandzadeh@va.gov
Phone:
COR: Gustavo J. Calleros, Healthcare Engineer
Email: gustavo.calleros@va.gov
Phone:
Exhibit A
Temporary Fire Water Shutdown at Buildings: 206, 256, 257 & 258 (691-21-120)
Area of Impact
As part of our continued effort to improve infrastructure across West Los Angeles Campus, construction crews will temporarily shut down fire water service to multiple buildings. The purpose of this shutdown is to transition the fire water supply to a new source as part of the long-term water improvement project on the VA campus. Please note that the Interim Life Safety Measures (ILSM) has been implemented for this task and the buildings will be under fire watch by VAPD during the shutdown. Please see the list of affected buildings and the water shutdown timeline below.
Contact(s)
If you have additional questions about this matter or require more information, please contact:
Khoa Do, Healthcare Engineer
Email: khoa.do1@va.gov
Phone:
UPDATED WLA Construction Advisory – B209 Water Connection. Temporary Two-lane closure of Patton Ave (691-21-120)
Area of Impact
As a part of our continued effort to improve infrastructure across VA West Los Angeles Campus, construction crews will be performing the following work for the installation of new water lines:
Construction crews will close off both traffic lanes on Patton Ave. between Bonsall Ave. & McArthur Ave. Patton Ave will be closed so through traffic will need to detour via Bonsall Ave. and McArthur Ave. Please see Exhibit A.
Dates & Times of Impact
Construction Start: 11/19/2024
Construction Finish: 11/20/2024
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Homa Shahpasandzadeh
Email: Homa.Shahpasandzadeh@va.gov
Phone:
COR: Gustavo Calleros
Email: Gustavo.Calleros@va.gov
Phone:
WLA Construction Advisory – Temporary Two-lane closure on Eisenhower Ave & Grant Ave, Southern portion of PL 18 & PL 10 (691-23-120)
Area of Impact
As a part of our continued effort to improve infrastructure across VA West Los Angeles Campus, construction crews will be performing the following work for the installation of new water lines:
Construction crews will close off the following areas. Please see Exhibit A:
• Both traffic lanes on Eisenhower Ave between Dewey Ave. as marked in Exhibit A
• Section of Grant Ave, between Pershing Ave & Dewey Ave and Southern portion of PL18.
• PL10
Dates & Times of Impact
Construction Start – 11/18/2024
Construction Finish – 01/15/2025
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Homa Shahpasandzadeh
Email: Homa.Shahpasandzadeh@va.gov
Phone:
COR: Gustavo Calleros
Email: gustavo.calleros@va.gov
Phone:
Temporary Water Shutdown at Building 205 (691-21-120)
Area of Impact
As part of our continued effort to improve infrastructure across West Los Angeles Campus, construction crews will temporarily shut down domestic water service to Building 205 on the WLA VA campus. The purpose of this shutdown is to transition the domestic water supply to a new source as part of the long-term water improvement project on the VA campus. Please see Exhibit A for map of shutdown location.
Portable restrooms and bottled water will be provided; please see Exhibit A for restroom locations.
Dates & Times of Impact
Construction Start – 11/18/24
Construction Finish – 11/18/24
Contact(s)
If you have additional questions about this matter or require more information, please contact:
Khoa Do, Healthcare Engineer
Email: khoa.do1@va.gov
Phone:
WLA Construction Advisory – West entrance to CTRS – Tiny Homes. Temporary road closure. (691-23-120)
Area of Impact
As a part of our continued effort to improve infrastructure across VA West Los Angeles Campus, construction crews will be performing the following work for the installation of new water lines:
Construction crews will close off two traffic lanes on the West entrance of CTRS, for the extension of new water lines. All pedestrian traffic will remain open. Please see Exhibit A.
Dates & Times of Impact
Construction Start: 11/14/2024
Construction Finish: 11/15/2024
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Homa Shahpasandzadeh
Email: Homa.Shahpasandzadeh@va.gov
Phone:
COR: Gustavo Calleros
Email: Gustavo.Calleros@va.gov
Phone:
WLA UTILITY SHUTDOWN NOTICE
Area of Impact
Construction crews are temporarily shutting down data/telecommunication service to the CTRS Admin Office Trailers 1, 2 and Dining Hall #801 to reconfigure the network at the Swing Admin Trailers (See Exhibit A).
Staff operating out of CTRS should plan accordingly so that their operations can continue during the shut-down.
Dates & Times of Impact
Start: 11/16/2024, 6 a.m.
End: 11/16/2024, 4:30 p.m.
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Gustavo Calleros
Email: Gustavo.Calleros@va.gov
Phone:
UPDATED WLA Construction Advisory – Installation of Perimeter Fence at CTRS (691-24-126)
Area of Impact
Construction crews will temporarily occupy The Great Lawn around CTRS to install pedestrian gates in the wrought iron perimeter fence. This area of The Great Lawn will be inaccessible to pedestrians and vehicles, but construction crews will place signage to re-direct traffic during construction. The Perimeter Fence Gate Install Locations are highlighted on the attached map (Exhibit A).
Dates & Times of Impact
• UPDATED Construction Start: Ongoing
• UPDATED Construction End: 11/14/2024, 4 p.m.
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Gustavo Calleros
Email: Gustavo.Calleros@va.gov
Phone:
UPDATED WLA Construction Advisory - Sanitary Sewer Pipe Installation (691-24-117)
Area of Impact
As a part of our continued effort to improve infrastructure across the West Los Angeles Campus, construction crews will be installing a new sanitary sewer pipe along Vandergrift Ave, Patton Ave, and Bonsall Ave. This construction work is to be conducted in multiple phases.
Dates & Times of Impact
Please refer to Exhibit A for details on all affected areas. The project encompasses 3 sections across the North Campus:
- UPDATED Zone 1 (Exhibit A; 11/12/2024 – 02/14/2025): Located from Patton Ave. through the historic walkway.
- UPDATED Zone 2 (Exhibit B; 03/03/2025 – 03/28/2025): Located on the southern portion of B258 along Vandergrift Ave.
- UPDATED Zone 3 (Exhibit A; 03/24/2025 – 05/02/2025): Located along Patton Ave.
- UPDATED Zone 4 (Exhibit A; 05/05/2025 – 05/23/2025): Located on the southern portion of B209 along Bonsall Ave.
Due to pipe installation work, Vandergrift Ave will be temporarily closed with sidewalks being available for pedestrians until 02/14/2025 and will have barricades to redirect traffic. Sections of Patton Ave., Vandergrift Ave., and Bonsall Ave. will be coned off, and flagmen will be present to direct both vehicle traffic and pedestrian traffic along the available walkway around the sewer line installation. Drivers should follow the crew’s signs and directions and proceed with caution, while pedestrians should exercise caution while walking on the surrounding sidewalks. Please also see below the Exhibits A and B showing the vehicular rerouting due to the road closure.
If you have additional questions about this matter or require more information, please contact:
COR: Khoa Do, Healthcare Engineer
Email: Khoa.Do1@va.gov
Phone:
COR: Gustavo Calleros
Email: Gustavo.Calleros@va.gov
Phone:
Exhibit A and B
WLA Construction Advisory – B209 Water Connection. Temporary Two-lane closure of Patton Ave (691-21-120)
Area of Impact
As a part of our continued effort to improve infrastructure across VA West Los Angeles Campus, construction crews will be performing the following work for the installation of new water lines:
Construction crews will close off both traffic lanes on Patton Ave., between Bonsall Ave. & MacArthur Ave. Due to this section closure, through traffic will need to detour via Bonsall Ave. and MacArthur Ave. Traffic control measures will be implemented throughout the duration of construction. Construction crews will place signage to redirect traffic and pedestrians. Flagmen will be directing traffic. Please see Exhibit A.
Dates & Times of Impact
Construction Start: 11/04/24
Construction Finish: 11/05/24
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Homa Shahpasandzadeh
Email: Homa.Shahpasandzadeh@va.gov
Phone:
COR: Gustavo Calleros
Email: Gustavo.Calleros@va.gov
Phone:
B206 Alternate Ingress and Egress Routes – Vandergrift Construction
Area of Impact
As a part of our continued effort to improve infrastructure across the West Los Angeles Campus, the AHSC street improvement project will be replacing sidewalk, landscaping, and installing new curb along Vandergrift Ave. Vandergrift will not be accessible from the south elevation of B206 as the contractor has installed fencing to separate public access from the construction zone. Staff and visitors area advised to follow the alternative ingress and egress paths as depicted in Exhibit A for the safest means of access.
The closure is highlighted on the attached map (Exhibit A).
Pedestrians should avoid the closure area and use the detours highlighted in Exhibit A.
Dates & Times of Impact
The alternate ingress and egress route timeline, based on the site condition, is as follows:
B206 Alternate Ingress and Egress Route Dates : Ongoing through 11/08/2025.
Contact(s)
If you have additional questions about this matter or require more information, please contact:
Noah Hamouche
Email: Noah.Hamouche@va.gov
Phone:
Roberto Clemente
Email: Roberto.Clemente@va.gov
Phone:
Dustin Koonce
Email: Dustin.Koonce@va.gov
Phone:
AHSC Vandergrift Ave Sidewalk Closure
Area of Impact
As a part of our continued effort to improve infrastructure across the West Los Angeles Campus, the AHSC street improvement project will be replacing sidewalk, landscaping, and installing new curb along Vandergrift Ave. Portions of sidewalk on the north and south sides of Vandergrift will be closed during this time. Pedestrians are advised to take the alternative detour routes indicated on the map from B258, B257, and B206. The contractor will implement traffic control signage and safety measures during construction to prevent pedestrians from entering the work zone. A one-lane closure will be necessary on Vandergrift Ave at various times during construction. Flagmen will be present during these intermittent one-lane closures to maintain smooth traffic flow through the street.
The sidewalk closure is highlighted on the attached map (Exhibit A).
Drivers are advised to follow signs and directions. Pedestrians should avoid the closure area and use the detours highlighted in Exhibit A.
Dates & Times of Impact
The present sidewalk closure timeline, based on the site condition, is as follows:
Vandergrift Ave Sidewalk Closure Dates : Ongoing through 11/08/2025
Contact(s)
If you have additional questions about this matter or require more information, please contact:
Noah Hamouche
Email: Noah.Hamouche@va.gov
Phone:
Roberto Clemente
Email: Roberto.Clemente@va.gov
Phone:
Dustin Koonce
Email: Dustin.Koonce@va.gov
Phone:
WLA Construction Advisory – Parking Lot 18 Deactivation Pershing One Lane Closure (691-24-101)
Area of Impact
As a part of our continued effort to improve infrastructure across West Los Angeles Campus, construction crews will close off one lane on Pershing Ave. between Dewey Ave. and Grant Ave. Traffic control measures will be implemented throughout the duration of construction. Construction crews will place signage to redirect traffic and pedestrians. Please see Exhibit A for closure area.
Dates & Times of Impact
- Construction Start: 11/04/2024
- Construction End: 11/27/2024
Exhibit A: Construction Area and Sidewalk Closure
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Homa Shahpasandzadeh, Healthcare Engineer
Email: Homa.Shahpasandzadeh@va.gov
Phone:
UPDATED WLA Construction Advisory – Installation of Perimeter Fence at CTRS (691-24-126)
Area of Impact
UPDATED As a part of our continued effort to improve infrastructure across VA West Los Angeles Campus, construction crews will temporarily occupy The Great Lawn around CTRS to install a 5’ tall wrought iron perimeter fence. This area of The Great Lawn will be temporarily inaccessible to pedestrians and vehicles, but construction crews will place signage to re-direct traffic during construction. The Perimeter Fence Install Location is highlighted on the attached map (Exhibit A). Materials will be delivered to the site beginning 9/16/2024 (Exhibit A).
Dates & Times of Impact (weather permitting)
• Construction Start: Ongoing
• UPDATED Construction End: 11/7/2024, 4:00 PM
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Gustavo J. Calleros, Healthcare Engineer
Email: gustavo.calleros@va.gov
Phone:
UPDATED WLA Construction Advisory – Sections of Nimitz Ave. Temporary Two-lane Closure (691-21-120)
Area of Impact
As a part of our continued effort to improve infrastructure across VA West Los Angeles Campus, the following work will take place for the extension of the water line:
- Construction crews will close off traffic lanes on Nimitz Ave between Bonsall Ave and Patton Ave across B256 & B404. The affected areas will be inaccessible to vehicular traffic. Additionally, the sidewalk on the west side of Bonsall Ave will be closed for the duration of the work. All pedestrian traffic will be required to cross to the east side of Bonsall Ave. Please see Exhibit A for details.
UPDATED Dates & Times of Impact (weather permitting)
Construction Start (Phase 6b): Ongoing
Construction Finish (Phase 6b): 10/25/2024
UPDATED Construction crews will close off one traffic lane on Nimitz Ave across B257, for the extension of new water lines. Additionally, the sidewalk on the west side of Bonsall Ave will be closed for the duration of the work. All pedestrian traffic will be required to cross to the east side of Bonsall Ave. Please see Exhibit B for details.
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Homa Shahpasandzadeh
Email: Homa.Shahpasandzadeh@va.gov
Phone:
COR: Gustavo J. Calleros, Healthcare Engineer
Email: gustavo.calleros@va.gov
Phone:
Exhibit A and B
WLA Construction Advisory Pershing Ave - Temporary 1 Lane Closure (691-21-120)
Area of Impact
As a part of our continued effort to improve infrastructure across VA West Los Angeles Campus, the following work will take place:
- Construction crew will close off 1 lane on Pershing Ave for terminal flush outs by B13. The sidewalks will be closed, and other parking locations will be available for use for the day. Traffic control measures will be implemented throughout the duration of construction. Construction crews will place signage to redirect traffic and pedestrians. Flagmen will be directing traffic. Please see Exhibit A for details.
Dates & Times of Impact (weather permitting)
Construction Start: 10/28/2024, 7:00 a.m.
Construction Finish:11/01/2024, 4:30 p.m.
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Homa Shahpasandzadeh
Email: Homa.Shahpasandzadeh@va.gov
Phone:
COR: Gustavo J. Calleros, Healthcare Engineer
Email: gustavo.calleros@va.gov
Phone:
Exhibit A
Sepulveda Construction Advisory - EUL Sepulveda Wet Utilities Assessment (691A4-23-219)
Area of Impact
As part of our ongoing efforts to enhance the VA Sepulveda campus infrastructure, construction crews will be conducting potholing across various sections of the campus.
During the potholing work, certain sections of the VA Sepulveda campus will be coned off to ensure pedestrian safety. Please follow the posted signs and directions from the crew, and proceed with caution in the areas detailed in Exhibits A, B, & C. This work will be executed in multiple phases.
Dates & Times of Impact
The project will be divided into 4 main sections:
- Phase 1 (Exhibit A; 10/21/2024 – 10/25/2024): Located along the North-East section of Sepulveda.
- Phase 2 (Exhibit B; 10/28/2024 – 11/01/2024): Located along the South-east section of Sepulveda.
- Phase 3 (Exhibit B; 11/04/2024 – 11/08/2024): Located along the South-west section of Sepulveda.
- Phase 4 (Exhibit C; 11/11/2024 – 11/15/2024): Located along the North-west section of Sepulveda
- If you have additional questions about this matter or require more information, please contact:
Contact(s)
COR: Khoa Do, Healthcare Engineer
Email: Khoa.Do1@va.gov
Phone:
COR: Gustavo J. Calleros, Healthcare Engineer
Email: gustavo.calleros@va.gov
Phone:
Exhibits A, B, & C
AHSC Bonsall & MacArthur Ave Intersection Closure
Area of Impact
As a part of our continued effort to improve infrastructure across the West Los Angeles Campus, the AHSC street improvement project will be repaving the intersection of Bonsall & MacArthur Ave. The intersection will be closed during this time.
The road closure is highlighted on the attached map (Exhibit A).
Drivers are advised to follow signs and directions to access the detour route and avoid the road closure. Pedestrians should avoid the closure area and use the detours highlighted in Exhibit A.
Dates & Times of Impact
The present road closure timeline, based on the site condition, is as follows:
Bonsall and MacArthur Ave Intersection Closure Dates: 10/21/2024 through 10/25/2024
Contact(s)
If you have additional questions about this matter or require more information, please contact:
Noah Hamouche
Email: Noah.Hamouche@va.gov
Phone:
Roberto Clemente
Email: Roberto.Clemente@va.gov
Phone:
Dustin Koonce
Email: Dustin.Koonce@va.gov
Phone:
Exhibit A:
WLA UTILITY SHUTDOWN NOTICE
Area of Impact
Construction crews shall be temporarily disconnecting water services to B509 (Recycle plant), UCLA Baseball field, and Cemetery (See Exhibit A for impacted areas on 10/19/2024)
Staff working in affected areas should make necessary arrangements to ensure their operations can continue smoothly during the water shutdown.
Date & Time of Impact
10/19/2024, 7 a.m. to 3:30 p.m.
Contact(s)
If you have additional questions about this matter or require more information, please contact:
Khoa Dang Do
Email: Khoa.Do1@va.gov
Phone:
UPDATED WLA Construction Advisory – Sections of Vandergrift Ave. Temporary Two-lane Closure & Bonsall Ave. Temporary Two-lane Closure (691-21-120)
Area of Impact
As a part of our continued effort to improve infrastructure across VA West Los Angeles Campus, the following work will take place for the extension of the water line:
Construction crews will close off traffic lanes on Vandergrift Ave. The work will occur in multiple locations between sections A, B and C. The remaining sections of Vandergrift Ave will be open while work is being completed in other sections. During each closure, through traffic will have to detour around Vandergrift Ave. The affected areas will be inaccessible to vehicular traffic. Sidewalks may be closed intermittently, and pedestrians will be rerouted to the south side of the street as needed. Alternate parking options are available in close proximity. Please see Exhibit A for details.
Dates & Times of Impact (weather permitting)
Construction Start (Phase 6b): Ongoing
Construction Finish (Phase 6b): 10/11/2024
Construction crews will close off traffic lanes on Nimitz Ave between Bonsall Ave and Patton Ave across B256 & B404. The affected areas will be inaccessible to vehicular traffic. Additionally, the sidewalk on the west side of Bonsall Ave will be closed for the duration of the work. All pedestrian traffic will be required to cross to the east side of Bonsall Ave. Please see Exhibit A for details.
Construction Start (Phase 6b): Ongoing
Construction Finish (Phase 6b): 10/25/2024
UPDATED Construction crews will close off traffic lanes on Nimitz Ave across B257, for the extension of new water lines. The affected areas will be inaccessible to vehicular traffic. Additionally, the sidewalk on the west side of Bonsall Ave will be closed for the duration of the work. All pedestrian traffic will be required to cross to the east side of Bonsall Ave. Please see Exhibit B for details.
Construction Start (Phase 6b): 10/28/2024
Construction Finish (Phase 6b): 11/12/2024
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Homa Shahpasandzadeh
Email: Homa.Shahpasandzadeh@va.gov
Phone:
COR: Gustavo Calleros
Email: Gustavo.Calleros@va.gov
Phone:
Exhibit A & B
WLA Construction Advisory - B220 Parking Lot Expansion Project (691-23-214)
Area of Impact
As a part of our continued effort to improve infrastructure across West Los Angeles Campus, construction will take place on the east of the B220 parking lot, access road to B506, and the parking lot adjacent to B506. No full road closure on Eisenhower is required. A temporary enclosure will be placed around the perimeter of construction for safety of the residents. The purpose is to seal coat and re-stripe the upper parking lot directly adjacent to B220. See Exhibit A for details.
Dates & Times of Impact
Construction crews will partially close Parking Lot 220 to seal existing cracks. See Exhibit A.
Construction Start: 10/4/2024
Construction End: 10/7/2024
Construction crews will partially close Parking Lot 220 to seal asphalt and re-stripe the lot. See Exhibit A.
Construction Start: 10/11/2024
Construction End: 10/15/2024
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Khoa Do
Email: Khoa.Do1@va.gov
Phone:
COR: Gustavo Calleros
Email: Gustavo.Calleros@va.gov
Phone:
Exhibit A
B404 (PL48) EUL Project - Domestic Water Connection
Area of Impact
As a part of our continued effort to improve infrastructure across the West Los Angeles Campus, the contractor for the B404 (PL48) EUL project will be connecting to the domestic water main on Bonsall Ave. The contractor will implement a one-lane closure at various times of construction. The contractor will implement traffic control signage, flagmen, and safety measures during construction.
The intermittent one-lane closure is highlighted on the attached map (Exhibit A).
Drivers are advised to follow signs and directions. Pedestrians should proceed with caution while walking around the area.
Dates & Times of Impact
The present road closure timeline, based on the site condition, is as follows:
Bonsall Ave Intermittent 1-Lane Closure Dates : Ongoing through 10/11/2024
Contact(s)
If you have additional questions about this matter or require more information, please contact:
Noah Hamouche
Email: Noah.Hamouche@va.gov
Phone:
Roberto Clemente
Email: Roberto.Clemente@va.gov
Phone:
Dustin Koonce
Email: Dustin.Koonce@va.gov
Phone:
Exhibit A
Updated WLA Construction Advisory - Sanitary Sewer Structural Lining and CCTV (691-24-117)
Updated Area of Impact
As a part of our continued effort to improve infrastructure across the West Los Angeles Campus, construction crews will conducting Structural Lining and CCTV work along South Campus from 5:00 PM – 3:00 AM Monday - Friday. This construction work is to be conducted in multiple phases.
Please refer to Exhibit A for details on all affected areas. The project encompasses 8 sections across most of South Campus:
1. Zone 1 (Exhibit B & C; 09/30/2024 – 10/04/2024): Located along the eastern portion of Dowlen Dr. from Parking Lot 43 through the southern portion of Building 523 and West of Dowlen Dr. northwest of Building 500.
2. Zone 2 (Exhibit D; 10/07/2024 – 10/11/2024): Located along the eastern portion of Dowlen Dr.
3. Zone 3 (Exhibit E; 10/14/2024 – 10/18/2024): Located along the northern portion of Parking Lot 43 and Building 523.
4. Zone 4 (Exhibit F; 10/21/2024 – 11/25/2024): Located along the western portion of Dowlen Dr. near Building 91 and 307.
5. Zone 5 (Exhibit G; 10/28/2024 – 11/01/2024): Located along the western portion of Dowlen Dr. from Building 312 up to Parking Lot 5.
6. Zone 6 (Exhibit H; 11/04/2024 – 11/08/2024): Located within section from Building 304, 345 and cutting across the northern portion of Parking Lot 3.
7. Zone 7 (Exhibit I; 11/11/2024 – 11/15/2024): Located on the northern portion of Building 345 and cutting across the northern portion of Parking Lot 3.
8. Zone 8 (Exhibit J; 11/18/2024 – 11/22/2024): Located on the northern portion of Parking Lot 3 and cutting across Sawtelle Blvd. from Building 525 to Parking Lot 1.
Due to the lining of pipes and CCTV, sections of South Campus will have single lane closures. The areas of affect will be coned off, and flagmen will be present to direct both vehicle and pedestrian traffic around the lining and CCTV work. Drivers should follow the crew’s signs and directions and proceed with caution, while pedestrians should exercise caution while walking on the surrounding sidewalks.
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Khoa Do, Healthcare Engineer
Email: Khoa.Do1@va.gov
Phone:
COR: Gustavo J. Calleros, Healthcare Engineer
Email: gustavo.calleros@va.gov
Phone:
AHSC Vandergrift Ave Sidewalk Closure
Area of Impact
As a part of our continued effort to improve infrastructure across the West Los Angeles Campus, the AHSC street improvement project will be replacing sidewalk, landscaping, and installing new curb along Vandergrift Ave. Portions of sidewalk on the north and south sides of Vandergrift will be closed during this time. Pedestrians are advised to take the alternative detour routes indicated on the map from B258, B257, and B206. The contractor will implement traffic control signage and safety measures during construction to prevent pedestrians from entering the work zone. A one-lane closure will be necessary on Vandergrift Ave. at various times during construction. Flagmen will be present during these intermittent one-lane closures to maintain smooth traffic flow through the street.
The sidewalk closure is highlighted on the attached map (Exhibit A).
Drivers are advised to follow signs and directions. Pedestrians should avoid the closure area and use the detours highlighted in Exhibit A.
Dates & Times of Impact
Vandergrift Ave Sidewalk Closure Dates : Ongoing through 10/25/2025
Contact(s)
If you have additional questions about this matter or require more information, please contact:
Noah Hamouche
Email: Noah.Hamouche@va.gov
Phone:
Roberto Clemente
Email: Roberto.Clemente@va.gov
Phone:
Dustin Koonce
Email: Dustin.Koonce@va.gov
Phone:
UPDATED WLA Construction Advisory – Sections of Vandergrift Ave. Temporary Two-lane Closure & Bonsall Ave. Temporary Two-lane Closure (691-21-120)
Area of Impact
As a part of our continued effort to improve infrastructure across VA West Los Angeles Campus, the following work will take place for the extension of the water line:
Construction crews will close off traffic lanes on Bonsall Ave. between Arnold Ave. and Nimitz Ave. The affected areas will be inaccessible to vehicular traffic. Please see Exhibit A for details.
Dates & Times of Impact
UPDATED Timeline: (Weather permitting)
Construction Start (Phase 7.3a): On-going
Construction Finish (Phase 7.3a): 09/30/2024
_______________________________________________________________________________________________
Construction crews will close off traffic lanes on Vandergrift Ave. The work will occur in multiple locations between sections A, B and C. The remaining sections of Vandergrift Ave will be open while work is being completed in other sections. During each closure, through traffic will have to detour around Vandergrift Ave. The affected areas will be inaccessible to vehicular traffic. Sidewalks may be closed intermittently, and pedestrians will be rerouted to the south side of the street as needed. Alternate parking options are available in close proximity. Please see Exhibit A for details.
UPDATED Timeline: (Weather permitting)
Construction Start (Phase 6b): 09/12/2024
Construction Finish (Phase 6b): 10/07/2024
_______________________________________________________________________________________________
Construction crews will close off traffic lanes on Nimitz Ave between Bonsall Ave and Patton Ave across B256 & B404. The affected areas will be inaccessible to vehicular traffic. Additionally, the sidewalk on the west side of Bonsall Ave will be closed for the duration of the work. All pedestrian traffic will be required to cross to the east side of Bonsall Ave. Please see Exhibit B for details.
UPDATED Timeline: (Weather permitting)
Construction Start (Phase 6b): 09/30/2024
Construction Finish (Phase 6b): 10/25/2024
_______________________________________________________________________________________________
UPDATED Construction crews will close off traffic lanes on Nimitz Ave Across B257, for the extension of new water lines. The affected areas will be inaccessible to vehicular traffic. Additionally, the sidewalk on the west side of Bonsall Ave will be closed for the duration of the work. All pedestrian traffic will be required to cross to the east side of Bonsall Ave. Please see Exhibit C for details.
Timeline (Weather permitting)
Construction Start (Phase 6b): 10/28/2024
Construction Finish (Phase 6b): 11/12/2024
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Homa Shahpasandzadeh
Email: Homa.Shahpasandzadeh@va.gov
Phone:
COR: Gustavo Calleros
Email: gustavo.calleros@va.gov
Phone:
South Campus Parking Lot Construction – Utility Trenching
Area of Impact
- West side of Sawtelle Boulevard, north of Dowlen Drive
- Sidewalk on the west side of Building 500
Dates & Times of Impact
September 23 – October 7, 2024
Monday through Friday, 7:00 A.M. to 3:30 P.M.
Contact(s)
If you have additional questions about this matter or require more information, please contact:
Metro Community Relations: Helyn Oshrin
Email: OshrinH@metro.net
Phone: 213.518.1915
VA Project Support: Andrew Culbertson
Email: aculbertson@concoursefederal.com
Phone: 804.467.9882
Exhibit A
Updated WLA Construction Advisory - Sanitary Sewer Pipe Installation and Point Repair (691-24-117)
Area of Impact
As a part of our continued effort to improve infrastructure across the West Los Angeles Campus, construction crews will be installing a new sanitary sewer pipe on Grant Ave along with a point repair and CCTV near B44. This construction work is to be conducted in multiple phases.
Please refer to Exhibit A for details on all affected areas. The project encompasses 3 sections across the SE section of the North Campus:
- UPDATE Zone 1 (Exhibit B; 09/30/2024 – 10/04/2024): Located between B44 and B299 within maintenance parking lot.
- UPDATE Zone 2 (Exhibit C; 10/07/2024 – 10/11/2024): Located East of B44 along Grant Ave.
Due to pipe installation work, a small section of Grant Ave will be temporarily closed. The area will be coned off, and flagmen will be present to direct both vehicle and pedestrian traffic around the sewer line installation. Drivers should follow the crew’s signs and directions and proceed with caution, while pedestrians should exercise caution while walking on the surrounding sidewalks.
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Khoa Do, Healthcare Engineer
Email: Khoa.Do1@va.gov
Phone:
COR: Gustavo J. Calleros, Healthcare Engineer
Email: gustavo.calleros@va.gov
Phone:
Exhibit A, B and C
Updated WLA Construction Advisory - Sanitary Sewer Pipe Installation and Point Repair (691-24-117)
Area of Impact
As a part of our continued effort to improve infrastructure across the West Los Angeles Campus, construction crews will be installing a new sanitary sewer pipe on Grant Ave along with a point repair and CCTV near B44. This construction work is to be conducted in multiple phases.
Please refer to Exhibit A for details on all affected areas. The project encompasses 3 sections across the SE section of the North Campus:
1. UPDATE Zone 1 (Exhibit B; 09/30/2024 – 10/04/2024): Located between B44 and B299 within maintenance parking lot.
2. UPDATE Zone 2 (Exhibit C; 10/07/2024 – 10/11/2024): Located East of B44 along Grant Ave.
Due to pipe installation work, a small section of Grant Ave will be temporarily closed. The area will be coned off, and flagmen will be present to direct both vehicle and pedestrian traffic around the sewer line installation. Drivers should follow the crew’s signs and directions and proceed with caution, while pedestrians should exercise caution while walking on the surrounding sidewalks.
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Khoa Do, Healthcare Engineer
Email: Khoa.Do1@va.gov
Phone:
COR: Gustavo J. Calleros, Healthcare Engineer
Email: gustavo.calleros@va.gov
Phone:
UPDATED WLA Construction Advisory – Dewey Ave & Eisenhower Ave. Temporary Two-lane closure & closing of PL17 (691-23-120)
Area of Impact
As a part of our continued effort to improve infrastructure across VA West Los Angeles Campus, construction crews will be performing the following work for the installation of new water lines:
Construction crews will close off both traffic lanes on Dewey Ave. between Grant Ave. and Pershing Ave. Dewey will be closed so through traffic will need to detour via Bonsall Ave. and Pershing Ave. Please see Exhibit A.
Timeline: (Weather permitting)
Dewey (a)
Updated: Construction Start: On-going
Updated: Construction Finish: 09/27/2024
Construction crews will close off traffic lanes on sections of Dewey Ave, Eisenhower Ave & closing off PL17. For alternative parking, use PL16 & PL18. The affected areas will be inaccessible to vehicular traffic. Sidewalks will remain open for the duration of the work. Please see Exhibit A.
Timeline: (Weather permitting)
Dewey (b)
Updated: Construction Start: 09/30/2024
Updated: Construction Finish: 11/18/2024
Eisenhower (c)
Updated: Construction Start: 09/30/2024
Updated: Construction Finish: 11/18/2024
_________________________________________________________________________________________________
Construction crews will be working on the landscaping area, the area is closed to public. This work will not impact any road or sidewalk closure.
Timeline: (Weather permitting)
Bringham (d)
Updated: Construction Start: On-going
Updated: Construction Finish: 11/04/2024
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Homa Shahpasandzadeh
Email: Homa.Shahpasandzadeh@va.gov
Phone:
COR: Gustavo Calleros
Email: gustavo.calleros@va.gov
Phone:
Updated WLA Construction Advisory - Sanitary Sewer Structural Lining and CCTV (691-24-117)
Updated Area of Impact
As a part of our continued effort to improve infrastructure across the West Los Angeles Campus, construction crews will be conducting Structural Lining and CCTV work along the South Campus from 5:00 PM – 3:00 AM Monday - Friday. This construction work is to be conducted in multiple phases.
Please refer to Exhibit A for an overview of all affected areas. The project encompasses 8 sections across most of the South Campus:
1. Zone 1 (Exhibit B & C; 09/23/2024 – 09/27/2024): Located along the eastern portion of Dowlen Dr. from Parking Lot 43 through the southern portion of Building 523 and west of Dowlen Dr. northwest of Building 500.
2. Zone 2 (Exhibit D; 09/30/2024 – 10/04/2024): Located along the eastern portion of Dowlen Dr.
3. Zone 3 (Exhibit E; 10/07/2024 – 10/11/2024): Located along the northern portion of Parking Lot 43 and Building 523.
4. Zone 4 (Exhibit F; 10/14/2024 – 10/18/2024): Located along the western portion of Dowlen Dr. near Building 91 and 307.
5. Zone 5 (Exhibit G; 10/21/2024 – 10/25/2024): Located along the western portion of Dowlen Dr. from Building 312 up to Parking Lot 5.
6. Zone 6 (Exhibit H; 10/28/2024 – 11/01/2024): Located within section from Building 304, 345 and cutting across the northern portion of Parking Lot 3.
7. Zone 7 (Exhibit I; 11/04/2024 – 11/08/2024): Located on the northern portion of Building 345 and cutting across the northern portion of Parking Lot 3.
8. Zone 8 (Exhibit J; 11/11/2024 – 11/15/2024): Located on the northern portion of Parking Lot 3 and cutting across Sawtelle Blvd. from Building 525 to Parking Lot 1.
Due to the lining of pipes and CCTV, sections of the South Campus will have single lane closures. The affected areas will be coned off, and flagmen will be present to direct both vehicle and pedestrian traffic around the lining and CCTV work. Drivers should follow the crew’s signs and directions and proceed with caution, while pedestrians should exercise caution while walking on the surrounding sidewalks.
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Khoa Do, Healthcare Engineer
Email: Khoa.Do1@va.gov
Phone:
COR: Gustavo J. Calleros, Healthcare Engineer
Email: gustavo.calleros@va.gov
Phone:
WLA Construction Advisory – Installation of Perimeter Fence at CTRS
Area of Impact
As a part of our continued effort to improve infrastructure across VA West Los Angeles Campus, construction crews will temporarily occupy The Great Lawn around CTRS to install a wrought iron perimeter fence. This area of The Great Lawn will be inaccessible to pedestrians and vehicles, but construction crews will place signage to re-direct traffic during construction. The Perimeter Fence Install Location is highlighted on the attached map (Exhibit A).
Dates & Times of Impact
- Construction Start: 9/16/2024, 7:00 A.M.
- Construction End: 10/31/2024, 4:00 P.M.
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Gustavo Calleros
Email: gustavo.calleros@va.gov
Phone:
Exhibit A: Construction Area
UPDATED WLA Construction Advisory – Sections of Vandergrift Ave. Temporary Two-lane Closure & Bonsall Ave. Temporary Two-lane Closure (691-21-120)
Area of Impact
As a part of our continued effort to improve infrastructure across VA West Los Angeles Campus, the following work will take place for the extension of the water line:
• Construction crews will close off traffic lanes on Bonsall Ave. between Arnold Ave. and Nimitz Ave. The affected areas will be inaccessible to vehicular traffic. Please see Exhibit A for details.
UPDATED Timeline: (Weather permitting)
Construction Start (Phase 7.3a): On-going
Construction Finish (Phase 7.3a): 09/27/2024
_______________________________________________________________________________________________
· Construction crews will close off traffic lanes on Vandergrift Ave. The work will occur in multiple locations between sections A, B and C. The remaining sections of Vandergrift Ave. will be open while work is being completed in other sections. During each closure, through traffic will have to detour around Vandergrift Ave. The affected areas will be inaccessible to vehicular traffic. Sidewalks may be closed intermittently, and pedestrians will be rerouted to the south side of the street as needed. Alternate parking options are available in close proximity. Please see Exhibit A for details.
UPDATED Timeline: (Weather permitting)
Construction Start (Phase 6b): 09/12/2024
Construction Finish (Phase 6b): 09/26/2024
_______________________________________________________________________________________________
· Construction crews will close off traffic lanes on Nimitz Ave. between Bonsall Ave. and Patton Ave across B256 & B404. The affected areas will be inaccessible to vehicular traffic. Additionally, the sidewalk on the west side of Bonsall Ave. will be closed for the duration of the work. All pedestrian traffic will be required to cross to the east side of Bonsall Ave. Please see Exhibit B for details.
UPDATED Timeline: (Weather permitting)
Construction Start (Phase 6b): 09/30/2024
Construction Finish (Phase 6b): 10/25/2024
_______________________________________________________________________________________________
• UPDATED Construction crews will close off traffic lanes on Nimitz Ave. Across B257, for the extension of new water lines. The affected areas will be inaccessible to vehicular traffic. Additionally, the sidewalk on the west side of Bonsall Ave. will be closed for the duration of the work. All pedestrian traffic will be required to cross to the east side of Bonsall Ave. Please see Exhibit C for details.
Timeline (Weather permitting)
Construction Start (Phase 6b): 10/28/2024
Construction Finish (Phase 6b): 11/12/2024
Contact(s)
If you have additional questions about this matter or require more information, please contact:
COR: Homa Shahpasandzadeh
Email: Homa.Shahpasandzadeh@va.gov
Phone:
COR: Gustavo J. Calleros, Healthcare Engineer
Email: gustavo.calleros@va.gov
Phone:
AHSC Nimitz Ave North Sidewalk Closure
Area of Impact
As a part of our continued effort to improve infrastructure across the West Los Angeles Campus, the AHSC street improvement project will be replacing sidewalk, landscaping, and installing new curb ramps along Nimitz Ave. Sidewalks on the north side of Nimitz will be closed during this time. Pedestrians are advised to take the accessible detour route via Bonsall Ave to Vandergrift Ave to reach B256 and B257. The contractor will implement traffic control signage and safety measures during construction.
The sidewalk closure is highlighted on the attached map (Exhibit A).
Drivers are advised to follow signs and directions. Pedestrians should avoid the closure area and use the detour highlighted in Exhibit A.
Dates & Times of Impact
Nimitz Ave North Sidewalk Closure Dates : 08/29/2024 through 01/31/2025
Contact(s)
If you have additional questions about this matter or require more information, please contact:
Noah Hamouche
Email: Noah.Hamouche@va.gov
Phone:
Roberto Clemente
Email: Roberto.Clemente@va.gov
Phone:
Dustin Koonce
Email: Dustin.Koonce@va.gov
Phone:
AHSC Gorham/Bringham Ave Closure (South Plaza)
Area of Impact
As a part of our continued effort to improve infrastructure across the West Los Angeles Campus, the AHSC street improvement project will repaving a portion of the Gorham Ave area just north of B264. The contractor will implement traffic control signage and safety measures during construction.
The road closure is highlighted on the attached map (Exhibit A).
Drivers are advised to follow signs and directions. Pedestrian access will be maintained, but should proceed with caution while walking around the area.
Dates & Times of Impact
The present road closure timeline, based on the site condition, is as follows:
Pershing and MacArthur Ave Closure Dates: 08/05/2024 through 11/29/2024
Contact(s)
If you have additional questions about this matter or require more information, please contact:
Noah Hamouche
Email: Noah.Hamouche@va.gov
Phone:
Roberto Clemente
Email: Roberto.Clemente@va.gov
Phone:
Dustin Koonce
Email: Dustin.Koonce@va.gov
Phone:
Exhibit A
AHSC Street Widening Project – MacArthur Ave Closure
Area of Impact
As a part of our continued effort to improve infrastructure across the West Los Angeles Campus, MacArthur Ave will remain closed as part of the AHSC street widening project on the north campus. The contractor will implement barricades, traffic control signage, and safety measures during construction.
The road closure is highlighted on the attached map (Exhibit A).
Drivers are advised to follow signs and directions. Pedestrians should proceed with caution while walking in the area.
Dates & Times of Impact (Weather permitting)
MacArthur Ave Closure Dates : 07/22/2024 thru 02/28/2025
Contact(s)
If you have additional questions about this matter or require more information, please contact:
Roberto Clemente
Email: Roberto.Clemente@va.gov
Phone:
Dustin Koonce
Email: Dustin.Koonce@va.gov
Phone:
Noah Hamouche
Email: Noah.Hamouche@va.gov
Phone: