Roseburg VA Construction Updates
Roseburg VA has many construction and expansion projects underway to enhance veterans' health care throughout our health care system. Each project is a tremendous opportunity to augment and improve the delivery of services to Veterans. We request your patience and cooperation as we collectively work towards transforming our facilities.
Roseburg VA Construction
The Engineering department is currently staffed by four Health Care Engineers overseeing 32 projects in various stages of construction. The total estimated cost for these projects is $663,046,000.
Roseburg VA campus major construction project highlights
Major project to replace Building 1
Pending VACO request to Congress for full funding in the next federal budget, to be released in March 2025
USACE, pending AE task order for site surveys (July award)
Design/construction award ETA, late 2026
Roseburg VA campus upgrades and enhancements
EDII – Electrical Deficiencies Phase II
All equipment is onsite; construction is 85% complete, ETA June 2024
Will provide backup to the entire campus
Campus HVAC
A-E identified a design error; a change order was issued to correct
Chiller plant commissioning is scheduled for July
Building 3 Remodel and Seismic Retrofit
Solicitation is pending for early July; the bid is to close in early August
Funding approved for FY25 Q1
Replace MRI
- Construction awarded to Skytek
Estimated construction complete January 2025
Electrical Survey
Engineering crew are working on campus one-lines; ETA September 2024
Door Replacement
Pending door install in ROI June 2024 and Bldg 57 (VA Police) in July 2024
Remodel Bldg 57 (VA Police)
Construction awarded; NTP July 2024
Remodel Bldg 1AC D Wing
Work underway; replacing ceiling tiles, paint, and all new flooring
Bldg 81 CLC Expansion
FY 25 construction; duration will be 18 months
The design is 95% complete
Current: The building has 18 beds that are single-occupancy
Each room shares a restroom with the adjoining room
After construction: There will be 32 beds
New rooms will have private restrooms
Seismic Retrofit Bldgs 11, 13 and 16
Pending AE selection; ETA September 2024
Construction Projects VA Clinic Leases
North Bend Expansion
Phase 3 transition to Phase 4; move date July 11 – 13
Phase 4 to begin June 2024
Recently completed projects
Upgrade boiler plant
- Seismically upgrade boiler plant and replace boilers
Campus fire alarm upgrade
- Upgrade the entire campus fire alarm system
Upgrade campus fence
- Installation and repair of 15,000 feet of the campus perimeter fence
Correct patient access walkways
- Construct, widen, and repair patient walkways to meet ADA (Americans with Disabilities Act) requirements
Remodel patient check-in
- Provide COVID-19 distancing for patient check-in
Pharmacy clean room
- Work to connect to emergency power
Remodel phlebotomy
- Expand and renovate blood draw
Update and expand the community living center
- Once this project is complete, we will have a total of 98 community living center beds on the Roseburg VA campus
Building 3 Temp Trailer Relocation for Swing Space
- Bldg 3 temp trailer renovation complete.