Skip to Content

Roseburg VA Construction Updates

Roseburg VA has many construction and expansion projects underway to enhance veterans' health care throughout our health care system. Each project is a tremendous opportunity to augment and improve the delivery of services to Veterans. We request your patience and cooperation as we collectively work towards transforming our facilities.

Roseburg VA Construction

The Engineering department is currently staffed by four Health Care Engineers overseeing 32 projects in various stages of construction. The total estimated cost for these projects is $663,046,000.

Roseburg VA campus major construction project highlights

  • Major project to replace Building 1

    • Pending VACO request to Congress for full funding in the next federal budget, to be released in March 2025​

    • USACE, pending AE task order for site surveys (July award)​

    • Design/construction award ETA, late 2026​

Roseburg VA campus upgrades and enhancements

  • EDII – Electrical Deficiencies Phase II

    • All equipment is onsite; construction is 85% complete, ETA June 2024​

    • Will provide backup to the entire campus​

  • Campus HVAC

    • A-E identified a design error; a change order was issued to correct​

    • Chiller plant commissioning is scheduled for July​

  • Building 3 Remodel and Seismic Retrofit

    • Solicitation is pending for early July; the bid is to close in early August 

    • Funding approved for FY25 Q1

  • Replace MRI

    • Construction awarded to Skytek​
    • Estimated construction complete January 2025

  • Electrical Survey​

    • Engineering crew are working on campus one-lines; ETA  September 2024​

  • Door Replacement​

    • Pending door install in ROI June 2024 and Bldg 57 (VA Police) in July 2024

  • Remodel Bldg 57 (VA Police)​

    • Construction awarded; NTP July 2024​

  • Remodel Bldg 1AC D Wing​

    • Work underway; replacing ceiling tiles, paint, and all new flooring​

  • Bldg 81 CLC Expansion ​

    • FY 25 construction; duration will be 18 months​

    • The design is 95% complete​

    • Current: The building has 18 beds that are single-occupancy​

      • Each room shares a restroom with the adjoining room​

    • After construction: There will be 32 beds​

      • New rooms will have private restrooms​

  • Seismic Retrofit Bldgs 11, 13 and 16​

    • Pending AE selection; ETA September 2024​

Construction Projects VA Clinic Leases

  • North Bend Expansion

    • Phase 3 transition to Phase 4; move date July 11 – 13​

    • Phase 4 to begin June 2024​

     

Recently completed projects

  • Upgrade boiler plant

    • Seismically upgrade boiler plant and replace boilers
  • Campus fire alarm upgrade

    • Upgrade the entire campus fire alarm system
  • Upgrade campus fence

    • Installation and repair of 15,000 feet of the campus perimeter fence
  • Correct patient access walkways

    • ​​​Construct, widen, and repair patient walkways to meet ADA (Americans with Disabilities Act) requirements
  • Remodel patient check-in

    • Provide COVID-19 distancing for patient check-in
  • Pharmacy clean room 

    • Work to connect to emergency power
  • Remodel phlebotomy

    • Expand and renovate blood draw
  • Update and expand the community living center 

    • Once this project is complete, we will have a total of 98 community living center beds on the Roseburg VA campus
  • Building 3 Temp Trailer Relocation for Swing Space

    • Bldg 3 temp trailer renovation complete.​